Columboola to Western Downs

Overview

Powerlink and Ergon Energy have identified the need for a new 275kV transmission line between the Western Downs Substation (near Kogan Creek Power Station), and the proposed Columboola Substation (adjacent to and connecting in to the Columboola Switching Station near Miles).

A new 100m wide easement will be required for this proposed transmission line, with additional space for a future line to meet longer-term electricity needs in the region.

Status

Powerlink is inviting submissions on its intention to seek Ministerial designation for the project. Further information about how to make a submission can be downloaded from the Newsletters & notices page.

The Final Environmental Impact Statement (EIS) for the project was published in December 2011. This document can be downloaded from the Environmental documents page. We would like to thank everyone who made a submission on the Draft EIS and who contributed to the Environmental Impact Assessment process undertaken by specialist environmental consultant Parsons Brinckerhoff (PB) from late 2010.  

Timeline

Project start Project finish

Contact name:
Email address
© Copyright Powerlink Queensland 2011   Terms & Conditions   Privacy statement   Contact us   Right to Information