Back to Consultations
 
Cost icon - $38.37 million
Calendar icon - October 2023

Project Specification Consultation Report Maintaining reliability of supply in the Cairns region Stage 1: Addressing the condition risks of the transmission towers between Davies Creek and Bayview Heights.

The majority of supply to the Cairns region is delivered through the inland 275kV network to Ross, near Townsville. From Ross it is transferred via a 275kV transmission line to Chalumbin, continuing via a second 275kV transmission line from Chalumbin to the Woree Substation on the outskirts of Cairns. These 275kV transmission lines also provide connections to the Mt Emerald Wind Farm and Kareeya Power Station.

Emerging condition risks due to structural corrosion on the 275kV transmission lines between Ross, Chalumbin and Woree substations puts at risk Powerlink’s ongoing compliance with the reliability and service standards set out in the National Electricity Rules (the Rules), Powerlink’s Transmission Authority and applicable regulatory instruments.

Given the non-homogenous condition of the transmission structures over the 348km transmission line route, and subject to the submissions received and cost-benefit analysis undertaken as part of this Regulatory Investment Test for Transmission (RIT-T) consultation, there is an opportunity to optimise potential reinvestments by applying a prudent and staged approach to address higher risk components in the nearer term based on deteriorating condition. 

The final 16km of the Chalumbin to Woree section of the transmission line requires priority action to address their more complex and advanced condition risks and has been proposed under Stage 1 of this RIT-T (Addressing the condition risks of the transmission towers between Davies Creek and Bayview Heights). 

Click to enlarge map.

 

The proposed preferred option that is considered to satisfy the RIT-T involves the selective replacement of corroded components and the full repaint of the impacted towers by October 2023.   

The indicative capital cost of the RIT T project for the preferred option is $38.37 million in 2020/21 prices.

Powerlink welcomes submissions from potential proponents who consider they may be able to offer a credible non-network option that is both economically and technically feasible to address the condition risks identified in the PSCR.

Submissions are due by COB Thursday, 8 July 2021. 

Powerlink anticipates the publication of a Project Assessment Conclusions Report in September 2021.  

In the context of engagement activities with consumers and the general community, Powerlink has assessed this project as 'normal' on the RIT-T stakeholder engagement matrix

A copy of the Project Specification Consultation Report is available below.