Back to Consultations
RIT-T Primary Equipment Icon
RIT-T Secondary Systems Replacement icon
RIT-T Costs 23.75 million Icon
RIT-T Calendar October 2022 Icon

 

Powerlink has recently published a 'Project Assessment Conclusions Report' to maintain reliability of supply at Kamerunga Substation.

Located approximately 10 kilometres north-west of Cairns, Kamerunga Substation, established in 1976, is a major injection point into the Ergon Energy distribution network.

Both the primary plant and secondary systems at Kamerunga Substation are nearing the end of their technical service lives with identified condition and obsolescence issues. The substation is also susceptible to major flooding events which could result in damage to equipment leading to loss of supply.

In accordance with the Regulatory Investment Test for Transmission (RIT-T), Powerlink published a Project Specification Consultation Report (PSCR) in September 2018, followed by the publication of the Project Assessment Draft Report (PADR) in April 2019. The PADR identified the preferred option; replacement of Kamerunga's current primary plant, installation of additional circuit breakers for the Woree feeders and the full replacement of all secondary systems in a new building by October 2022.

Both the PSCR and PADR invited submissions on credible non-network options, which could address the identified need. There were no submissions received in response to either the PSCR or PADR.

The outcomes of the economic analysis contained in the PACR remain unchanged from those published in the PADR. Consequently, the draft recommendation to implement the preferred option has been adopted without change as the final recommendation in the PACR.

The RIT-T project involves replacing Kamerunga's current primary plant with new AIS equipment, installation of additional circuit breakers for the Woree feeders and the full replacement of all secondary systems in a new building by October 2022. All primary plant and secondary systems are to be located above the 1 in 200 year flood level. The estimated capital cost of the project is $23.75 million in 2018/19 prices.  Powerlink is the proponent of the proposed network project.

In the context of engagement activities with consumers and the general community, Powerlink has assessed this project as 'normal' on the RIT-T Stakeholder Engagement Matrix.