Contingent projects are network investments above a defined threshold that are not included in revenue allowances upfront, but for which a defined regulatory pathway exists once a trigger is met. This pathway provides a structured and transparent way to progress these investments when the need for them becomes sufficiently certain, ensuring customers do not pay for them earlier than necessary, while still enabling delivery once clear evidence supports the need.
A project may be treated as contingent where it is identified in a Revenue Determination as reasonably foreseeable but insufficiently certain to include at the time, or where the Australian Energy Market Operator (AEMO) identifies it as an actionable Integrated System Plan (ISP) project. In either case, progression requires submission of a Contingent Project Application (CPA) to the Australian Energy Regulator (AER) to seek approval for cost recovery.
There are two main ways a project becomes a contingent project:
A project is identified by Powerlink in its Revenue Proposal as potentially needed but insufficiently certain, so it is listed as a contingent project. Subject to the AER’s decision, it is included in the Revenue Determination but excluded from the revenue allowance. If Powerlink considers that defined trigger events set out in the Revenue Determination have occurred, it may seek an amendment to the Revenue Determination.
When AEMO identifies a project as an actionable ISP project it is automatically treated as a contingent project, even if not included in Powerlink’s Revenue Determination.
Contingent projects may also arise in response to changes to regulatory requirements, such as network solutions to address new system strength obligations.
In any case, a Regulatory Investment Test for Transmission (or RIT-T) is completed first to determine the option that best meets the identified need, with the Contingent Project Application then assessing the efficiency of the preferred option identified in the RIT-T.
Progressing a contingent project requires a formal application to be made by Powerlink to the AER known as a Contingent Project Application.
This structured process is designed to ensure transparency, certainty and consumer protection.
A contingent project starts as a potential investment where uncertainty exists about its timing, scope or materiality. In practice, such projects may be driven by changes in energy demand, generator retirements, market or policy developments, or emerging system security and stability needs. Evidence often comes from planning assessments and AEMO’s inputs. A trigger event defines the point at which sufficient certainty exists for the project to proceed through applicable investment processes and be considered for regulatory approval.
A project can only move forward when a credible trigger event(s) — defined clearly and objectively — has occurred. Acceptable triggers must:
Where an ISP project is declared ‘actionable’ by AEMO, it is treated as a contingent project even if it was not identified in a revenue determination.
For these projects, the trigger must include:
Once a credible trigger event(s) occurs and the need for a contingent project becomes sufficiently certain, the project may move into the CPA process. This process has several stages:
Before lodging a CPA, Powerlink can meet with the AER to ensure there is a shared understanding of:
This engagement can help prepare for statutory assessment timelines and supports the submission of a complete, well evidenced application.
After the trigger event(s) has occurred and pre-lodgement engagement is complete, Powerlink may formally lodge the CPA to the AER. A compliant application must provide:
If the application is compliant, the AER accepts it and the AER’s formal assessment process begins.
The AER’s detailed review includes:
The AER may request additional information and may draw on engineering, benchmarking or financial experts as required.
Consultation on a CPA gives stakeholders the opportunity to:
The AER considers all submissions and responds to issues raised as part of its final decision. This public process ensures transparency and strengthens the quality of regulatory oversight.
The AER’s assessment period can vary but it must make its decision within 40 business days from either the date it receives the application, or the date it receives any additional information required to make its decision, whichever is later. The 40 business days can be extended by a further 60 business days for complex assessments.
At the end of its assessment, the AER may:
If approved, the AER issues an amended Revenue Determination reflecting the revenue required to deliver the project. Cost recovery then commences from the applicable regulatory year, depending on when the CPA was lodged.