The Regulatory Investment Test for Transmission (RIT-T) has been extended to apply to replacement expenditure planning from 18 September 2017.

RIT-T for replacement expenditure planning

The Australian Energy Market Commission extended the application of the Regulatory Investment Test for Transmission (RIT-T) to replacement expenditure planning as of 18 September 2017.

Transitional arrangements

Powerlink has a number of projects that were expected to become committed during the transitional period between 18 September 2017 to 30 January 2018 and were therefore be excluded from the RIT-T process. Once the committed project criteria are fulfilled, details of any such projects are to be published on Powerlink’s website in compliance with rule 11.99 of the National Electricity Rules.

Project nameScheduled completion dateProject descriptionProject commissioned
Callide A/Calvale 132kV transmission reinvestmentAugust 2021At Calvale Substation establish a second 275/132kV transformer.30 July 2021
Garbutt 132/66kV transformers replacement30 August 2019At Garbutt Substation remove both of the existing transformers from service and replace with two new 100MVA 132/66kV transformers.25 July 2019
Dysart transformer replacementJuly  2024At Dysart Substation replacement of both of the existing 132/66/22kV transformers with two new 132/66/11kV transformers. 
Dysart primary plant replacement30 June 2020At Dysart Substation full replacement of 132kV primary plant and selected replacement of 132kV secondary systems.October 2019
Line refit works on the 275kV transmission line between Woolooga and Palmwoods SubstationsJune 2023Between Woolooga and Palmwoods Substations selective replacement of 275kV steel structure components.September 2023
Ashgrove West Substation replacementJune 2022At Ashgrove West Substation replacement of selected 110kV primary plant and secondary systems.July 2021
Gin Gin Substation rebuildJune 2022At Gin Gin Substation replacement and reconfiguration of the 275kV and 132kV switchyards.November 2021
Line refit works on the 132kV transmission line between Eton Tee and Alligator Creek SubstationDecember 2025Between Eton Tee and Alligator Creek refit and paint of the 132kV structures. 
Calvale and Callide B secondary systems replacementDecember 2024At Calvale Substation and Callide B Power Station replacement of the majority of 275/132kV secondary systems equipment and panels and removal of redundant equipment.