Back to Consultations
RIT-T PSCR Tennyson

Powerlink has published a Project Specification Consultation Report (PSCR) to maintain reliability of supply and address condition risks at Tennyson Substation.

Tennyson Substation was established in 2001 to provide an injection point into the Energex distribution network to supply power to the Southern Brisbane and CBD area. Planning studies confirm there is an enduring need for Tennyson Substation to maintain the supply of electricity to the Brisbane area and meet legislative requirements.

The condition of one of its three transformers (Transformer 3) could place the network at risk of operating with load at risk or not meeting all supply needs.

Powerlink must therefore take action to avoid the increasing likelihood of loss of power arising from failure of the aging Transformer equipment and a range of deterioration issues.

The PSCR outlines Powerlink’s proposal to address the risks at Tennyson Substation by a like for like replacement of 110/33kV 80MVA Transformer 3 by October 2027. The indicative capital cost of the RIT-T project for the preferred option is $9.69 million in 2026 prices.

Submissions on the PSCR are due by 30 June 2026 and should be emailed to [email protected]. More details on how to make a submission are in the PSCR document.

In the context of engagement activities with customers and the general community, Powerlink has assessed this RIT-T project as ‘minor’ on the RIT-T stakeholder engagement matrix.

A copy of the PSCR is below.