Powerlink is delivering the transmission connection for Hyosung Group’s 100MW/200MWh (two-hour) BESS at Tangkam, west of Toowoomba.
Once operational, the Tangkam BESS will store surplus daytime solar energy for release during evening demand peaks, providing energy support for an estimated 150,000 households.
Powerlink’s work includes establishing a new 110kV feeder bay at Powerlink's Tangkam Substation and connecting the transmission line to customer‑owned infrastructure.
The design phase has been completed, and civil construction is nearing completion.
Powerlink’s works are scheduled for commissioning in Q2 2027.