2024
end October 2024
Regulatory Milestone
Powerlink notify AER to start Framework and Approach Process
end November 2024
Regulatory Milestone
AER consult on need for Framework and Approach
mid December 2024
Regulatory Milestone
AER Notice on Framework and Approach
On 10 December 2024, the AER issued a decision to replace Powerlink’s Framework and Approach.
2025
12 February 2025
19 March 2025
March 2025
Regulatory Milestone
AER publish Positions Paper
15 April 2025
Engagement Activity
Revenue Proposal Reference Group - Additional Meeting
22 May 2025
June 2025
Regulatory Milestone
Powerlink lodge Expenditure Forecasting Methodology with AER
11 June 2025
July 2025
Regulatory Milestone
AER publish Framework and Approach Paper
Read the Framework and Approach paper on the AER's website.
16 July 2025
21 August 2025
September 2025
Regulatory Milestone
Powerlink publish draft Revenue Proposal
17 September 2025
15 October 2025
12 November 2025
2026
end January 2026
Regulatory Milestone
Powerlink lodge Revenue Proposal with AER
March 2026
Regulatory Milestone
AER publish Issues Paper
April 2026
Regulatory Milestone
AER Public Forum on Revenue Proposal
May 2026
Regulatory Milestone
Submissions close on Issues Paper/Revenue Proposal
end September 2026
Regulatory Milestone
AER publish Draft Decision
October 2026
Regulatory Milestone
AER Pre-determination Conference
December 2026
Regulatory Milestone
Powerlink lodge Revised Revenue Proposal with AER
2027
end April 2027
Regulatory Milestone
AER publish Final Decision
January 2027
Regulatory Milestone
Submissions close on Revised Revenue Proposal
1 July 2027
Regulatory Milestone