Transmission plays a critical role in enabling the state’s economic growth and maintaining a reliable electricity system for households, businesses, and industries.
The Priority Transmission Investment (PTI) framework is established under Part 5 of the Energy (Infrastructure Facilitation) Act 2024. The framework provides a process for the Queensland Government to identify and assess major transmission investments and, where appropriate, direct Powerlink to construct those projects and recover efficient costs following completion of assessment activities.
A proactive approach benefits all stakeholders:
The Priority Transmission Investment process consists of four key stages leading up to the commencement of construction:
The Responsible Ministers identify a project as an eligible Priority Transmission Investment project.
The Responsible Ministers declare the eligible Priority Transmission Investment to be a candidate Priority Transmission Investment, and direct Powerlink to undertake an assessment of the project. The assessment stage comprises two sub-steps, each involving consultation by Powerlink. These sub-steps are the ‘candidate Priority Transmission Investment submission’ and ‘candidate Priority Transmission Investment’ assessment steps.
Powerlink builds the transmission infrastructure.
The Responsible Ministers may review any additional expenditure for efficiency including receiving advice from a suitably qualified person.
The process is intended to emulate the Regulatory Investment Test for Transmission (RIT-T), included in the National Electricity Rules (NER) and supporting documentation, as appropriately and closely as practicable.
For each project progressing through the framework, Powerlink undertakes two public consultations as part of the Assessment Stage:
The timeframes for the Priority Transmission Investment, including consultation timeframes, are set by the Responsible Ministers when directing Powerlink to undertake each step of the Assessment Stage.
Powerlink invites written responses to each consultation from energy industry participants, energy market bodies, potential non-network solution providers and any other interested parties.
Information on what is in and out of scope of the consultation is provided as part of the consultation process.
Priority Transmission Investments may comprise opportunities for non-network solutions. Potential providers of non-network solutions are encouraged to provide written response to the consultation, for full assessment of all credible options.
JOIN OUR REGISTER OF Non-Network Service Providers