Back to Reports

The Transmission Annual Planning Report (TAPR) is a technical document aimed at people who are familiar with the electricity industry.

The Australian Energy Regulator's (AER’s) TAPR Guidelines published in December 2018 set out the required format of Transmission Annual Planning reports, in particular additional data (TAPR templates) which must be publicly available to complement the TAPR document. 

The purpose of the TAPR templates is to provide a set of consistent data across the National Electricity Market (NEM) to assist customers and stakeholders to make informed decisions. Please note that the data is not intended to be relied upon explicitly for the evaluation of investment decisions and interested parties are encouraged to contact Powerlink in the first instance. 

Data is published in one of three template 'types' as required by the AER. The template type (transmission connection point/line segment/new generator connection) relates to the proposed technical nature of the proposed reinvestment or new generator connections data and should be read in conjunction with Chapter 5 Future Network Development, Chapter 8 Renewable Energy of the TAPR  and the Generation Capacity Guide

Please contact [email protected] if you require further assistance.

275_132kV substation establishment to maintain supply to Turkinje substation

Far North - Line Segment - 10 years xlsx

Line refit works on sections of the 275kV transmission lines between Greenbank and Mudgeeraba substations

Gold Coast - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Bergins Hill, Goodna and Belmont substations

Moreton - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission line between Blackstone and Abermain substations

Moreton - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission line between Mudgeeraba substation and Terranora

Gold Coast - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission line between Richlands and Algester substations

Moreton - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission lines between Belmont and Murarrie substations

Moreton - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission lines between Swanbank, Redbank Plains and West Darra substations

Moreton - Line Segment - 10 years xlsx

Line refit works on the 132kV transmission line between Callemondah and Gladstone South substations

Gladstone - Line Segment - 5 years xlsx

Line refit works on the 132kV transmission line between Nebo Substation and Eton Tee

North - Line Segment - 10 years xlsx

Line refit works on the 132kV transmission line between Ross and Dan Gleeson substations

Ross - Line Segment - 10 years xlsx

Line refit works on the 132kV transmission lines between Collinsville, Strathmore and Clare South substations

Ross - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Bergins Hill and Karana Downs

Moreton - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Bouldercombe and Nebo Substations

Central West - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Karana Downs and South Pine

Moreton - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Larcom Creek substation and Mt Miller

Gladstone - Line Segment - 5 years xlsx

Line refit works on the 275kV transmission line between Mt Miller and Bouldercombe substation

Gladstone - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Raglan and Larcom Creek substations

Gladstone - Line Segment - 10 years xlsx

Line refit works on the northern end of the 275kV transmission lines between Strathmore and Ross substations

Ross - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Woolooga and South Pine substations

Wide Bay - Line Segment - 5 years xlsx

Line refit works on the 275kV transmission lines between Chalumbin and Woree substations

Far North - Line Segment - 5 years xlsx

Line refit works on the 275kV transmission lines between Gin Gin and Woolooga substations

Wide Bay - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Raglan and Bouldercombe substations

Gladstone - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission lines between Ross and Chalumbin substations

Far North - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Wurdong and Boyne Island

Gladstone - Line Segment - 5 years xlsx

Rebuild the 132kV transmission line between Woree and Kamerunga substations

Far North - Line Segment - 10 years xlsx

Line refit works on the 132kV transmission line between Callide A, Biloela and Moura substations

Central West - Line Segment - 10 years xlsx

Replacement of the 110kV underground cable between Upper Kedron and Ashgrove West substations

Moreton - Line Segment - 5 years xlsx

Targeted Reinvestment in the 275kV transmission line between Calliope River (Wurdong Tee) and Gin Gin substations

Wide Bay - Line Segment - 10 years xlsx

Targeted reinvestment in the 275kV transmission line between Calliope River and (Wurdong Tee) Wurdong substations

Wide Bay - Line Segment - 5 years xlsx

Abermain 110kV secondary systems and primary plant replacement

Moreton - Connection Point - 10 years xlsx

Alan Sherriff 132kV secondary systems replacement

Ross - Connection Point - 5 years xlsx

Algester 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Alligator Creek 132kV primary plant replacement

North - Connection Point - 5 years xlsx

Alligator Creek SVC and 132kV secondary systems replacement

North - Connection Point - 10 years xlsx

Ashgrove West 110kV secondary systems replacement

Moreton - Connection Point - 5 years xlsx

Barron Gorge 132kV secondary systems replacement

Far North - Connection Point - 10 years xlsx

Biloela 132kV secondary systems replacement

Central West - Connection Point - 5 years xlsx

Blackwater 132kV primary plant replacement

Central West - Connection Point - 5 years xlsx

Blackwater 132kV secondary systems replacement

Central West - Connection Point - 10 years xlsx

Bowen North 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

Broadsound 275kV primary plant replacement

Central West - Connection Point - 10 years xlsx

Broadsound 275kV secondary systems replacement

Central West - Connection Point - 10 years xlsx

150MVAr 300kV bus reactor at Broadsound substation

Central West - Connection Point - 5 years xlsx

Bulli Creek 330_132kV transformer replacement

Bulli - Connection Point - 10 years xlsx

Bundamba 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Callemondah 132kV primary plant and secondary systems replacement

Gladstone - Connection Point - 5 years xlsx

Calvale 275kV primary plant replacement

Central West - Connection Point - 10 years xlsx

Chalumbin 275kV and 132kV primary plant replacement

Far North - Connection Point - 10 years xlsx

Chalumbin 275kV and 132kV secondary systems replacement

Far North - Connection Point - 5 years xlsx

Chinchilla 132kV substation replacement

South West - Connection Point - 5 years xlsx

Clare South 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

Columboola 132kV secondary systems replacement

Surat - Connection Point - 10 years xlsx

Edmonton 132kV secondary systems replacement

Far North - Connection Point - 5 years xlsx

El Arish 132kV secondary systems replacement

Far North - Connection Point - 10 years xlsx

Garbutt 132kV secondary systems replacement

Ross - Connection Point - 5 years xlsx

Gin Gin 275kV secondary systems replacement

Wide Bay - Connection Point - 10 years xlsx

Goodna 110_33kV transformer augmentation

Moreton - Connection Point - 10 years xlsx

Goodna 275kV and 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Greenbank SVC and 275kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Ingham South 132kV secondary systems replacement

Ross - Connection Point - 5 years xlsx

Innisfail 132kV secondary systems replacement

Far North - Connection Point - 5 years xlsx

Kamerunga 132_22kV transformer replacement

Far North - Connection Point - 10 years xlsx

Kemmis 132_66kV kV transformer replacement

North - Connection Point - 10 years xlsx

Larcom Creek 275kV secondary systems replacement

Gladstone - Connection Point - 10 years xlsx

Lilyvale 132kV secondary systems replacement

Central West - Connection Point - 5 years xlsx

Loganlea 275kV primary plant replacement

Moreton - Connection Point - 10 years xlsx

Mackay 132_33kV transformer replacement

North - Connection Point - 10 years xlsx

Middle Ridge 275kV and 110kV secondary systems replacement

South West - Connection Point - 10 years xlsx

Millmerran 330kV AIS secondary systems replacement

Bulli - Connection Point - 5 years xlsx

Molendinar 275kV secondary systems replacement

Gold Coast - Connection Point - 10 years xlsx

Mudgeeraba 110kV secondary systems replacement

Gold Coast - Connection Point - 5 years xlsx

Mudgeeraba 275_110kV Transformer replacement

Gold Coast - Connection Point - 10 years xlsx

Mudgeeraba 275kV and 110kV primary plant replacement

Gold Coast - Connection Point - 5 years xlsx

Murarrie 110kV secondary systems replacement

Moreton - Connection Point - 5 years xlsx

Nebo 132_11kV transformer replacements

North - Connection Point - 5 years xlsx

Newlands 132kV primary plant replacement

North - Connection Point - 5 years xlsx

North Goonyella 132kV secondary systems replacement

North - Connection Point - 5 years xlsx

Oakey 110kV secondary systems replacement

South West - Connection Point - 10 years xlsx

Palmwoods 275kV and 132kV primary plant replacement

Wide Bay - Connection Point - 10 years xlsx

Pioneer Valley 132kV primary plant replacement

North - Connection Point - 10 years xlsx

Redbank Plains 110kV primary plant and 110_11kV transformer reinvestments

Moreton - Connection Point - 5 years xlsx

Rockhampton 132kV secondary systems replacement

Gladstone - Connection Point - 5 years xlsx

Rocklea 110kV primary plant replacement

Moreton - Connection Point - 10 years xlsx

Rocklea 275_110kV transformer replacement

Moreton - Connection Point - 10 years xlsx

Ross 275kV and 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

South East Queensland bus reactors

Moreton - Connection Point - 5 years xlsx

South Pine 275_110kV transformer life extension

Moreton - Connection Point - 5 years xlsx

South Pine 275kV primary plant replacement

Moreton - Connection Point - 10 years xlsx

South Pine SVC secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Strathmore 275kV and 132kV partial secondary systems replacement - Stage 2

North - Connection Point - 10 years xlsx

Strathmore SVC secondary systems replacement

North - Connection Point - 5 years xlsx

Sumner 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Tarong 275_66kV transformer replacements

South West - Connection Point - 5 years xlsx

Tarong 275kV primary plant replacement

South West - Connection Point - 5 years xlsx

Tarong 275kV secondary systems replacement

South West - Connection Point - 10 years xlsx

Teebar Creek secondary systems replacement

Wide Bay - Connection Point - 10 years xlsx

Townsville East 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

Townsville South 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

Tully 132_22kV transformer replacement

Far North - Connection Point - 5 years xlsx

Turkinje 132kV primary plant replacement

Far North - Connection Point - 10 years xlsx

West Darra 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Woolooga 275kV and 132kV primary plant and secondary systems replacement

Wide Bay - Connection Point - 10 years xlsx

Woree 275kV and 132kV secondary systems replacement

Far North - Connection Point - 10 years xlsx

Yabulu South 132kV secondary systems replacement

Far North - Connection Point - 10 years xlsx

Yarwun 132kV secondary systems replacement

Gladstone - Connection Point - 10 years xlsx

2020 New Generator Connections Data

Statewide - Generation Data - Not Applicable xlsx

Line refit works on the 132kV transmission lines between Townsville South and Ross substations

Ross - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between South Pine and Palmwoods substations

Wide Bay - Line Segment - 10 years xlsx