Overview

The Gawara Baya Wind Farm Connection Project will connect Copenhagen Infrastructure Partner’s (CIP) Gawara Baya Wind Farm to Powerlink’s transmission network via our Guybal Munjan Switching Station in Mount Fox. 

The project will include:

  • expansion of the existing Guybal Munjan Switching Station footprint
  • two 275kV single circuit transmission lines
  • six transmission poles
  • access tracks.

The works will remain largely within the existing switching station land owned by Powerlink plus a small section of the adjoining Knuckledown Road reserve. 

The Gawara Baya Wind Farm and associated transmission line was previously being delivered by Windlab before it was acquired by CIP in August 2026. CIP will deliver the wind farm and transmission line works. For more information on the wind farm project, please visit gawarabaya.com

Powerlink owns, develops, operates and maintains the high voltage electricity transmission network in Queensland. We also provide electricity transmission services, including connecting large electricity generators (such as wind and solar farms), to the transmission network. 

Powerlink will facilitate the connection of the Gawara Baya Wind Farm and associated transmission line infrastructure to the electricity network via the Guybal Munjan Switching Station. 

Status

Powerlink takes our environmental responsibilities seriously and we are committed to comprehensively managing any potential environmental impacts resulting from our proposed activities for this project.

State environment and planning approvals 

Powerlink’s proposed amendment to the Genex Kidston Connection Project Ministerial Infrastructure Designation (MID) for the Gawara Baya Wind Farm Connection Project has been approved.

The project’s MID amendment application (AID-0126-0990) was approved on 4 September 2026 and took effect from 11 September 2026.  This process was managed by the Department of State Development, Infrastructure and Planning (DSDIP) with input from other government agencies.

The amended MID Decision Notice and Gazette Notice is available to view on this webpage under ‘Resources’. It is also available to view on DSDIP’s webpage here: Ministerial Infrastructure Designations public register.

Commonwealth environmental approvals

In July 2025, Powerlink referred the project to the Department of Climate Change, Energy, the Environment and Water (DCCEEW) for assessment under the Environment Protection and Biodiversity Conservation Act 1999 (the EPBC Act). The EPBC Act is Australia’s national environmental law. It protects and manages Australia’s ‘nationally significant’ animals, plants, habitats and places. 

We submitted this referral because environmental studies found there will be some activities in the project area that may impact protected species and habitat listed under the EPBC Act. 

Following a 10-business day public consultation period in August 2025 and DCCEEW’s review of Powerlink’s referral (2025/10246), the project was deemed not a ‘Controlled Action’. 

More information, including a copy of the referral decision, is available on the department's website. Search for ‘2025/10246’ under ‘EPBC number’.

Planning for delivery of Powerlink’s connection project is underway with construction anticipated to start in March 2027.

Community engagement 

Powerlink will continue to keep landholders, Traditional Owner groups, the community and other key stakeholders up to date as the project progresses. If you have any questions, please contact us at [email protected] or phone 07 4034 7600. 

Landholders with an existing easement on their property are also welcome to contact our Landholder Relations Advisor, Roisin McDonald, on 0429 562 360 or email [email protected].

Details

North

Substation

In Progress

Map

Contact

North Queensland Project Engagement Team

07 4034 7600

Gawara Baya Wind Farm Connection Project Timeline

July 2025

EPBC referral

August 2025

EPBC referral statutory engagement

September 2025

EPBC referral decision

January 2026

MID amendment lodgement

Q1 2026*

MID statutory engagement

Q2 2026*

Decision on MID amendment

March 2027

Start of construction

Full timeline