The Transmission Annual Planning Report (TAPR) is a technical document aimed at people who are familiar with the electricity industry.

The Australian Energy Regulator's (AER’s) TAPR Guidelines published in December 2018 set out the required format of Transmission Annual Planning reports, in particular additional data (TAPR templates) which must be publicly available to complement the TAPR document.

The purpose of the TAPR templates is to provide a set of consistent data across the National Electricity Market (NEM) to assist customers and stakeholders to make informed decisions. Please note that the data is not intended to be relied upon explicitly for the evaluation of investment decisions and interested parties are encouraged to contact Powerlink in the first instance.

Data is published in one of three template 'types' as required by the AER. The template type (transmission connection point/line segment/new generator connection) relates to the proposed technical nature of the proposed reinvestment or new generator connections data and should be read in conjunction with Chapter 5 Future Network Development, Chapter 8 Renewable Energy of the TAPR  and the Generation Capacity Guide.

Please contact [email protected]  if you require further assistance.

Line refit works on the 275kV transmission lines between Ross and Chalumbin substations

Far North - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission lines between Chalumbin and Woree substations

Far North - Line Segment - 5 years xlsx

Ingham South 132kV secondary systems replacement

Ross - Connection Point - 5 years xlsx

Barron Gorge 132kV secondary systems replacement

Far North - Connection Point - 5 years xlsx

Edmonton 132kV secondary systems replacement

Far North - Connection Point - 10 years xlsx

Woree to Kamerunga 132kV transmission line replacement

Far North - Line Segment - 5 years xlsx

Woree 275_132kV secondary systems replacement

Far North - Connection Point - 10 years xlsx

Cairns 132kV secondary systems replacement

Far North - Connection Point - 5 years xlsx

Innisfail 132kV secondary systems replacement

Far North - Connection Point - 5 years xlsx

Chalumbin 275kV and 132kV primary plant replacement

Far North - Connection Point - 10 years xlsx

Turkinje 132kV primary plant replacement

Far North - Connection Point - 10 years xlsx

Tully 132_22kV transformer replacement

Far North - Connection Point - 5 years xlsx

Kamerunga 132kV substation replacement

Far North - Connection Point - 5 years xlsx

Line refit works on the coastal 132kV transmission line between Clare South and Townsville South substations with network reconfiguration

Ross - Line Segment - 5 years xlsx

Line refit works on the 132kV transmission lines between Collinsville, Strathmore and Clare substations

Ross - Line Segment - 10 years xlsx

Townsville East 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

King Creek 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

Strathmore 275kV and 132kV partial secondary systems replacement

Ross - Connection Point - 5 years xlsx

Garbutt 132kV secondary systems replacement

Ross - Connection Point - 10 years xlsx

Strathmore SVC secondary systems replacement

Ross - Connection Point - 10 years xlsx

Townsville South 132kV secondary systems replacement_2029

Ross - Connection Point - 10 years xlsx

Alan Sherriff 132kV secondary systems replacement

Ross - Connection Point - 5 years xlsx

Line refit works on the 275kV transmission line between Strathmore and Ross Substations

North - Line Segment - 5 years xlsx

Line refit works on the 132kV transmission line between Ross and Dan Gleeson substations

Ross - Line Segment - 10 years xlsx

Line refit works on the 132kV transmisson lines between Townsville south and Ross substations

North - Line Segment - 5 years xlsx

Pioneer Valley 132kV primary plant replacement

North - Connection Point - 10 years xlsx

Line refit works on the 132kV transmission line between Nebo Substation, Eton tee and Pioneer Valley Substation

North - Line Segment - 10 years xlsx

Alligator Creek 132kV primary plant replacement

North - Connection Point - 5 years xlsx

Newlands 132kV primary plant replacement

North - Connection Point - 5 years xlsx

Kemmis 132kV secondary systems replacement

North - Connection Point - 5 years xlsx

North Goonyella 132kV secondary systems replacement

North - Connection Point - 5 years xlsx

Nebo 132_11kV transformer replacements

North - Connection Point - 5 years xlsx

Stanwell 275kV primary plant replacement

Gladstone - Connection Point - 10 years xlsx

Rebuild the 132kV transmission lines from Callide A to Biloela and Moura

Central West - Line Segment - 10 years xlsx

Lilyvale primary plant and transformers replacement

Central West - Connection Point - 5 years xlsx

Broadsound 275kV primary plant replacement

Central West - Connection Point - 10 years xlsx

Broadsound 275kV secondary systems replacement

Central West - Connection Point - 10 years xlsx

Lilyvale 132kV secondary systems replacement

Central West - Connection Point - 10 years xlsx

Biloela 132kV secondary systems replacement

Central West - Connection Point - 10 years xlsx

Blackwater 132_66_11kV transformers replacement

Central West - Connection Point - 5 years xlsx

Calvale 275kV primary plant replacement

Central West - Connection Point - 5 years xlsx

Rockhampton 132kV secondary systems replacement

Central West - Connection Point - 10 years xlsx

Line refit works on the 132kV transmission line between Bouldercombe to Egans Hill substations

Central West - Line Segment - 10 years xlsx

Line refit works on the 132kV transmission line between Bouldercombe and Stanwell substations

Central West - Line Segment - 10 years xlsx

QAL South 132kV secondary systems replacement

Gladstone - Connection Point - 10 years xlsx

Line refit works on the 132kV transmission line between Callemondah and Gladstone South substations

Gladstone - Line Segment - 5 years xlsx

QAL West 132kV secondary systems replacement

Gladstone - Connection Point - 5 years xlsx

Gladstone South 132kV secondary systems replacement

Gladstone - Connection Point - 5 years xlsx

Line refit works on the 275kV transmission line between Larcom Creek Substation and Mt Miller

Gladstone - Line Segment - 5 years xlsx

Rebuild the 275kV transmission lines between Wurdong tee and Gin Gin substation

Central West - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission lines between Gin Gin and Woolooga substations

Wide Bay - Line Segment - 10 years xlsx

Partial rebuild of the transmission line between Calliope River and Gin Gin substations

Wide Bay - Line Segment - 5 years xlsx

Line refit works on the 275kV transmission line between Woolooga and South Pine substations

Wide Bay - Line Segment - 5 years xlsx

Line refit works on the 275kV transmission line between South Pine and Palmwoods substations

Wide Bay - Line Segment - 10 years xlsx

Woolooga 275k and 132kv secondary systems replacement

Wide Bay - Connection Point - 10 years xlsx

Teebar Creek secondary systems replacement

Wide Bay - Connection Point - 10 years xlsx

Woolooga SVC secondary systems replacement

Wide Bay - Connection Point - 10 years xlsx

Line refit works on the 275kV transmission lines between Calliope River substation and Wurdong tee

Central West - Line Segment - 5 years xlsx

Line refit works on the 275kV transmission lines between Belmont and Murarrie substations

Moreton - Line Segment - 5 years xlsx

South Pine 275kv primary plant replacement_2026

Moreton - Connection Point - 10 years xlsx

Greenbank 275kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Bundamba 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Loganlea 275kV primary plant replacement

Moreton - Connection Point - 10 years xlsx

Rocklea 110kV primary plant replacement

Moreton - Connection Point - 10 years xlsx

Rocklea 275_110kV transformer replacement

Moreton - Connection Point - 10 years xlsx

Line refit works on the 110kV transmission line between South Pine and Upper Kedron substations

Moreton - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Bergins Hill and Karana Downs

Moreton - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission line between Rocklea to Sumner to West Darra

Moreton - Line Segment - 10 years xlsx

Goodna 110kV and 275kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Murarrie 110kV secondary systems replacement

Moreton - Connection Point - 5 years xlsx

Ashgrove West 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Sumner secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Greenbank SVC secondary systems replacement

Moreton - Connection Point - 10 years xlsx

South Pine SVC secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Algester 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Line refit works on the 110kV transmission line between Richlands and Algester substations

Moreton - Line Segment - 10 years xlsx

Replacement of the 110kV underground cable between Upper Kedron and Ashgrove West substations

Moreton - Line Segment - 5 years xlsx

West Darra 110kV secondary systems replacement

Moreton - Connection Point - 10 years xlsx

Line refit works on the 110kV transmission line between Blackstone and Abermain substations

Moreton - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission lines between Swanbank, Redbank Plains and West Darra

Moreton - Line Segment - 10 years xlsx

South Pine 275_110kV transformer replacement

Moreton - Connection Point - 10 years xlsx

Line refit works on the 275kV transmission line between Karana Downs and South Pine

Moreton - Line Segment - 10 years xlsx

Line refit works on the 110kV transmission line between West Darra and Upper Kedron substations

Moreton - Line Segment - 10 years xlsx

Mudgeeraba 110kV secondary systems replacement_2025

Gold Coast - Connection Point - 10 years xlsx

Line refit works on the 110kV transmission line between Mudgeeraba substation and Terranora

Gold Coast - Line Segment - 10 years xlsx

Targeted line refit works on sections of the 275kV transmission lines between Greenbank and Mudgeeraba substations

Gold Coast - Line Segment - 10 years xlsx

Mudgeeraba 275kV secondary systems replacement

Gold Coast - Connection Point - 5 years xlsx

Molendinar 275kV secondary systems replacement

Gold Coast - Connection Point - 5 years xlsx

Mudgeeraba 275kV and 110kV primary plant replacement_2026

Gold Coast - Connection Point - 10 years xlsx

Oakey 110kV secondary systems replacement

South West - Connection Point - 10 years xlsx

Bulli Creek transformer replacement

Bulli - Connection Point - 10 years xlsx

Mt England 275kV secondary systems replacement

Moreton - Connection Point - 5 years xlsx

Chinchilla 132kV primary plant replacement

South West - Connection Point - 5 years xlsx

Chinchilla 132kV secondary systems replacement

South West - Connection Point - 10 years xlsx

Tarong 275kV primary plant replacement

South West - Connection Point - 5 years xlsx

Tarong 275_66kV transformers replacement

South West - Connection Point - 5 years xlsx

Bulli Creek 132kV secondary systems replacement

Bulli - Connection Point - 5 years xlsx

Millmerran 330kV AIS secondary systems replacement

Bulli - Connection Point - 10 years xlsx

Middle Ridge 275kV and 110kV secondary systems replacement

Bulli - Connection Point - 10 years xlsx

Middle Ridge 110kV primary plant replacement

Bulli - Connection Point - 10 years xlsx

Line refit works on the 275kV transmission line between Raglan and Larcom Creek substations

Gladstone - Line Segment - 10 years xlsx

Line refit works on the 275kV transmission line between Mt Miller and Bouldercombe substation

Gladstone - Line Segment - 10 years xlsx

Line refits works on the 275kV transmission line between Wurdong and Boyne Island

Gladstone - Line Segment - 5 years xlsx

Broadsound 84MVAr bus reactor

Central West - Connection Point - 5 years xlsx

New generator connections data

Statewide - Generation Data - Not Applicable xlsx

Redbank Plains 110kV primary plant and 110_11kV transformers replacement

Moreton - Connection Point - 5 years xlsx